1. Allow wet work, such as
plaster and concrete work, to dry completely.
2. Water-proofing and flashing work should be completed.
Windows and doors should be in place and glazed.
3. Conduits and duct work should be completed.
4. Care should be taken to place air-conditioning vents and other
mechanical fixtures conveniently within the suspension system.
5. Installation should be done when relative humidity is not
greater than 80%.
Avoid installing the materials if relative humidity exceeds 80%.
6. There should be adequate ventilation in the installation area
if the building is new and humid conditions prevail.
Before beginning installation, make certain that there is no
condensation on the wall surfaces. Also, heating
system should be operating if the water or installation area is
particularly cold.
7. Damaged or soiled materials should be replaced.